THE REAL DEAL ON THE FIRST ENERGY-GPU MERGER & RATE CASE
Roger Odisio, PhD, Citizen Power Economist
July 19, 2001
Introduction
On November 9, 2000, FirstEnergy (Akron, Ohio) and General Public
Utilities, Inc. (GPU) (Morristown, N.J., Metropolitan Edison and
Pennsylvania Electric Companies in Pennsylvania) filed a merger
application with the Pennsylvania Public Utility Commission. On
November 29, 2000, Met-Ed and Penelec filed a petition at the PUC
seeking permission to implement an
"interim deferral tracking mechanism" that would allow GPU to recover
its excess Provider Of Last Resort (POLR) costs from customers. GPU
projected substantial losses due to the difference between what it can
charge its customers for power and what it has to pay for that power at
the wholesale level. The PUC consolidated these proceedings.
The law requires that applicants must demonstrate by a preponderance of
the evidence that a merger will "affirmatively promote the service,
accommodation, convenience or safety of the public in some substantial
way."
On June 20 the PUC issued an order adopting a proposed Settlement in
the FE/GPU joint merger and rate case, despite the fact that the
Settlement was opposed by almost twice as many parties (9) as signed it
(5). As required by the Settlement, the Order adopts the Administrative
Law Judge's (ALJ) Recommended Decision with a few minor changes,
approves the merger, and resolves GPU's request for rate relief to pay
its excessive POLR costs.
Citizen Power has been a party to settlements in the past. As
such, we recognize that settlement results are usually far short of
what is desired. Although there are provisions in this Settlement that
are the result of negotiating efforts by Citizen Power, we oppose the
Settlement that was finally approved because, as this paper will show,
if implemented, it is likely to cause harm to the environment and to
GPU ratepayers.
Executive Summary
On June 20, the PUC adopted a proposed Settlement that threatens
both consumers' pocketbooks and Pennsylvania air quality. At a time
when competition lies dormant and the very viability of
“ElectriChoice”
is in doubt, the PUC approved the FirstEnergy/GPU merger despite the
Companies' failure to show it (1) would not harm competition, and (2)
offered substantial net benefits to customers. The PUC also refused to
consider the likely degradation of Pennsylvania's air quality from
FirstEnergy's plan to run its dirty coal plants more extensively to
help meet GPU's load; or the potential financial impact a pending
Department of Justice lawsuit against FirstEnergy for alleged Clean Air
Act violations could have on FirstEnergy’s fitness to merge.
The Settlement may actually significantly reduce the amount GPU
would have contributed to the Sustainable Development Fund from 2005
through 2007. FirstEnergy promises to spend $10 million on a laundry
list of “broadly defined” energy related projects, but retains
full
control of how that money will be spent.
Besides approving the merger, the Settlement tries to resolve
GPU's claims of substantial losses in meeting its POLR obligations due
to the rise in wholesale prices for power. However, the Settlement
offers very different "solutions" depending on whether or not the
merger is consummated.
If the merger is consummated, contrary to what was ordered in
the 1998 Restructuring Settlement, GPU will be allowed to collect
excess POLR costs instead of stranded costs through its Competitive
Transition Charge (CTC ). The stranded costs, including payments to
Non-utility Generators (NUGs), will be deferred for later collection.
GPU will collect as much of its POLR costs as it can through the CTC,
at a rate fixed by the settlement, through 2010. Any remaining amount
must be written off. However, the deferred stranded costs can be
recovered in a five-year period beginning in 2011.
This means that customer rates between 2011 and 2015 are likely to be
higher than they would have been without the Settlement. Moreover, the
deferrals of stranded costs can only be accomplished by illegally
reneging on the stranded cost payments to NUGs, which were not only
established by GPU's Restructuring Settlement, but also contractually
obligated under the terms of the Public Utility Regulatory Policies Act
(PURPA). The Order directs the money supposed to be paid to NUGs to
instead be used to pay some of GPU's POLR costs.
If the merger is not consummated, consumers will be much worse
off. The deferral of stranded costs that was designed to maintain GPU's
rate caps will be eliminated. GPU will be guaranteed dollar for dollar
recovery of all of its excess POLR costs from June 1 to approximately
the end of the year. This means that, despite widely reported headlines
to the contrary, customer rates will be increased. And because power is
much more expensive in the summer, the total rate increase paid by
customers will be substantial--it is likely to exceed $150 million for
2001 alone.
After that, continued recovery of POLR costs throughout the
rest of the transition period (lasting perhaps until 2020 in some
cases) has been made easy by the PUC's finding that the decisions that
led to the problem, including GPU's sell-off of its generation, were
prudently made. The PUC's order is also likely to make it easier for
other Pennsylvania utilities to recover POLR costs, thereby weakening
price cap protection.
Discussion
The Order does the following:
(1) Approves the FirstEnergy-GPU merger without even evaluating its
potential effect on retail competition, or requiring the Companies to
show substantial net benefits, or to quantify merger savings and share
them with customers.
(2) Rejects consideration of both the potential harmful
environmental consequences of the merger and the potential financial
impact of the DOJ/EPA suit against FirstEnergy alleging Clean Air Act
violations.
(3) Finds that, despite clear evidence to the contrary, GPU is
entitled to recover its excess POLR costs because the decision to sell
its generation plants was prudent and it could not earn a fair return
without rate relief.
(a) If the merger is consummated, permits POLR cost recovery
(instead of stranded costs) through the CTC, but without raising total
revenue from generation rates ("price to compare" + CTC) through 2010.
The stranded costs will be deferred for recovery beginning in 2010. At
that time, however, GPU would have greater certainty of collecting
them, thus likely raising customer rates.
(b) If the merger is not
consummated for any reason, (1)
guarantees GPU recovery of all POLR costs from June 1 until the PUC
issues a new order after a hearing (probably at the end of the year),
and (2) provides an easy basis for recovery of POLR costs for the rest
of the transition period (which could last to 2020) by finding that GPU
acted prudently in divesting its power plants and relying on a
combination of selling off its POLR obligations and wholesale market
power purchases.
(4) Changes parts of the 1998 GPU Restructuring
Settlement,
including the amount of contributions to the GPU Sustainable
Development Fund, without the agreement of several parties to the
Restructuring Settlement.
Citizen Power opposes the Settlement adopted in the Order for several
reasons:
(1) The Companies failed to show, as they are required to do,
that the merger will not adversely affect competition in retail markets
and will provide substantial public benefits.
(2) The Order fails to address the merger's likely adverse
effect on Pennsylvania air quality and the potential financial impact
on FirstEnergy customers from the DOJ/EPA lawsuit. It substantially
reduces the GPU Sustainable Development Fund amount for 2005-2008 that
was approved in the 1998 GPU restructuring proceeding.
(3) GPU is not entitled to recover its excess POLR costs
because they are the result of the Company's own failed restructuring
strategy.
(4) If the merger is abandoned, it guarantees GPU dollar for dollar
recovery of most of this year's POLR costs and establishes an easy
basis for GPU to collect POLR costs for the rest of the transition
period. In addition, it is likely to enable other POLR providers to
more easily
recover excess costs from ratepayers.
(5) In its attempt to resolve GPU's problem of excessive POLR
costs, the PUC has not only misinterpreted The Electric Generation
Customer Choice and Competition Act (Act) standards for rate increases,
but also illegally altered several terms of GPU's Restructuring
Settlement without the consent of the signatory parties to that
agreement.
THE MERGER CASE
The Order approves the merger without explanation and despite the fact
that the Companies failed to meet several of their burdens to show the
merger would be in the public interest. The Order's assertion (p. 74),
without any facts or analysis to support it, that the merger "is
not likely to result in anti-competitive or discriminatory conduct, or
in the unlawful exercise of market power" merely regurgitates statutory
language. The record does not even contain a definition of the relevant
retail market--the Companies offered none--let alone any analysis of
the effect the merger would have on it. It is utterly meaningless for
the PUC to talk, as the Order does, of anti-competitive conduct without
reference to a specific market. For that reason alone the merger cannot
lawfully be approved.
The ALJ found that the wholesale market is noncompetitive. Retail
competition is essentially dormant throughout Pennsylvania as well. No
retail suppliers currently offer service at or below the "price to
compare" in any utility service area in the state. Surely, then, this
is not the time to approve a merger that further reduces the number of
potential suppliers without clear evidence it will not further harm
competition. FirstEnergy and GPU offered no such evidence.
The Order's finding that the merger would produce substantial,
affirmative net benefits, is unsupported by the record. It is clear
that the Companies decided to merge without first conducting any
analysis about potential benefits to the public. As a result, the
Companies provided a list of benefits that consisted almost entirely of
boons to shareholders and claims about an absence of an adverse affect.
In short, the Companies' merger benefit claims are nothing but vague
abstractions without any commitment for substantial benefits to the
public. They
cannot provide a basis to approve the merger.
Merger Savings
Unlike other mergers, the Companies offered neither an acceptable
quantification of merger savings nor a commitment to share them with
customers. The ALJ recommended
extending transmission and distribution (t&d) rate caps as a
"benefit" to customers, presumably as a way to capture some unspecified
share of savings for customers. But with no clear evidence that such an
extension would benefit ratepayers, this was largely an empty gesture.
In fact, some parties argued that t&d rates appear to be excessive,
so extending them would actually be a detriment to ratepayers.
Stating that the lack of evidence in the record about both the
role FirstEnergy will play in assisting GPU post-merger and the
quantification of merger savings "makes it impossible, at this point,
to approve the disposition of the merger savings", Commissioner
Fitzpatrick's May 24 Motion set the disposition of merger savings for
further discussion in the collaborative that led to the Settlement. The
Motion was later given effect by one of the PUC’s June 20 Orders.
Yet the Settlement does not even address either the quantification, or
the disposition, of merger savings. Rather, it simply requires the PUC
to adopt in its June 20 Order the ALJ's position it found "impossible"
to accept in its May 24 Motion. No explanation is offered for this
obvious contradiction. As a result, FirstEnergy stockholders will be
free to keep all savings from the merger.
Environmental Impacts
Citizen Power, along with the Clean Air Council and the
PennFuture Parties, raised serious concerns about the potential harmful
consequences of merger consummation: (1) the increased pollution from
FirstEnergy running its dirty coal plants more extensively to meet GPU
demand after the merger, and (2) the potential financial harm to GPU
customers from the DOJ lawsuit filed on behalf of the EPA alleging
Clean Air Act violations at FirstEnergy's Sammis Plant.
The Order rejected our contentions. The PUC simply found all
environmental effects of the merger to be beyond its jurisdiction,
despite: (a) the Commission's mandate to protect the public interest,
(b) the Commission's undeniable ability to condition a merger, as it
did in this Order, so as to make it acceptable, as long as the
condition reflects something that results from the merger, and (c) the
language in section 2811(21) of the Act which specifically notes that
environmental impacts are a public interest that the PUC should
consider.
In addition, the Settlement will likely lower the amount of money that
was to be added to the GPU Sustainable Development Funds. Under the GPU
Restructuring Plan, the fund would have gained an estimated increase of
$8.2 million from $0.01/kWh charge from 2005 through 2007, if
distribution rates are unchanged. The Settlement freezes current
distribution rates through 2007 and substitutes the $0.01/kWh charge
with a one-time FirstEnergy payment of $5 million to the GPU
Sustainable Development Funds, for a potential net decrease of millions
of dollars.
FirstEnergy promises to spend an additional $10 million on a laundry
list of very "broadly defined" energy projects that may or may not
include renewable sources. FirstEnergy will decide what projects will
be funded. Given the Company's environmental record, Citizen Power is
not optimistic about how FirstEnergy will spend these funds.
Citizen Power simply could not agree to a deal that ignores the
harmful environmental consequences of the merger, substantially reduces
GPU's Sustainable Fund, and offers only FirstEnergy promises to invest
in “broadly defined” energy supply and demand side
initiatives.
THE POLR CASE
Is GPU entitled to recover excess POLR costs?
In its June 20 Order, the PUC unequivocally found that GPU met
the standard under the Act for recovering its excess POLR costs from
customers. The order claims GPU met both prongs of the statutory test
for rate relief: (1) GPU's decision to sell off its generation was
prudent at the time it was made, but it left the company at the mercy
of wholesale prices over which it has no control, and (2) as a result,
without rate relief, GPU would be unable to earn a fair rate of return.
By accepting the settlement, the PUC had to make such a finding
and offer some arguments to support it, however weak they are, for the
following reasons. First, the Settlement requires that, except for a
few minor modifications, the PUC adopt the ALJ's decision in its
entirety. The ALJ found that GPU was entitled to rate relief from its
POLR costs. The PUC had to either agree with this finding or reject the
Settlement outright; no changes are permitted without the signatory
parties’ agreement.
Second, the PUC may not simply accept a Settlement as in the public
interest, but must be able to justify its decision with stated reasons
that take account of objections to the Settlement. That is especially
critical, where, as here, about twice as many parties refused to
support the Settlement as signed it. Even if the Settlement did not
specifically require the adoption of the ALJ's finding, to approve it,
the PUC would still have had to make a finding that GPU was entitled to
relief because some parts of the Settlement require rate relief.
In deciding if GPU was responsible for its predicament, and,
if so, should bear the consequences, however, the issue is not, as the
Order claims, whether GPU's decision to sell off its generation was
somehow prudent, but whether it was prudent for GPU to do so without
making reasonable
provision for its POLR obligations. GPU decided to rely on a
combination of (a) auctioning off its POLR obligation and (b) the
wholesale market, to supply power to its remaining customers. In
particular, relying on the spot wholesale market for significant
supply, as GPU did, was a risky choice in light of evidence of market
price volatility.
Had wholesale prices been driven lower by, for example, vigorous
competition, GPU could have earned extra profits for its stockholders
beyond a "fair return. It's safe to conclude that GPU would not have
filed with the PUC for permission to refund that money to customers.
But prices soared instead. GPU must now bear the consequences of its
decision. For markets to work to lower prices and achieve efficiency,
bad decisions must be penalized just as surely as good ones are
rewarded. GPU is not entitled to have customers fund its losses.
Moreover, whether or not the PUC's decision to allow POLR cost
recovery in this case is a legal precedent binding it in future cases,
such a finding severely damages deregulation in Pennsylvania. Other
utilities may at times have to pay soaring wholesale power costs. The
PUC's Order paves the way for them to collect these costs from
ratepayers, thereby punching holes in existing rate caps. These
utilities will now have an even better argument for passing them
through to customers than that offered by GPU because they still own
generation and only partially rely on wholesale markets for power.
In addition, in explaining its reasoning that GPU cannot earn a
fair return without rate relief, the PUC contradicts itself. GPU
inappropriately excluded transmission and distribution (t&d)
revenue in estimating its returns. The Order recognizes this: "Since we
believe that an appropriate analysis of the rate of return issue should
include a consideration of t&d revenues, we are not satisfied to
rely solely on these rate of return projections to support a grant of
relief under Section 2804 (iii) (D)." (Order at 18). Other parties in
the case showed that if t&d revenues were included, GPU would be
able to earn a reasonable return. The PUC does not cite this evidence,
or any evidence to the contrary. Yet, inexplicably, the PUC
nevertheless concludes that the Companies have demonstrated they cannot
earn a fair return. To say the least, this is not reasoned decision
making.
In sum, the Companies failed to show either that their actions
that led to the POLR costs were prudent, or that they cannot earn a
fair return without rate relief.
Will rates go up if the merger is consummated?
If the merger is consummated, the Order provides no additional revenue
from customers through 2010, yet the PUC claims that GPU's financial
problems with excessive POLR costs will be solved. However, the order
does provide for likely rate increases starting in 2011 to enable GPU
to collect stranded costs that were replaced in the CTC by POLR cost
collections.
The Order sets up separate accounts to keep track of POLR
costs and stranded costs beginning the first of this year. Originally
the CTC was designed to recover GPU's stranded costs at a rate
established by the Restructuring Settlement. Under this new Settlement,
if the merger is
consummated, the CTC will instead be used to recover POLR costs
incurred through 2005. When POLR costs for a particular year exceed the
amount that can be collected through the CTC, the difference will be
deferred and collected whenever possible, through 2010. Any remaining
POLR costs will be written off at that time. The stranded costs
displaced by POLR
recovery will be deferred and GPU will have the opportunity to collect
them for five years beginning in 2011.
Here is an example of how it works. Suppose GPU may collect $100
through its CTC, but has incurred $150 in POLR costs. It will collect
$100 of its POLR costs and defer the remaining $50 for possible
collection some time before the end of 2010. It will also defer the
$100 in stranded costs it would have passed through the CTC for
collection from 2011 through 2015.
As part of the Settlement, the CTC has been reduced a small amount and
the price to compare correspondingly raised, so the total rate
customers pay for both (assuming they buy from GPU) is unchanged
through 2010. The PUC trumpets it's holding of the line on the rate
caps: "By
this Settlement, all generation rates are frozen through 2010." Order
at 15. That is a true, though disingenuous, statement. GPU will not
collect one penny more from customers under the Settlement through 2010
than it would have collected without it. However, in making this claim,
repeated afterward in headlines around the state, the Order
deliberately ignores the last five years covered by the agreement, from
2011 through 2015. The Order's claims about rate impacts must be judged
on the whole fifteen-year period covered by the agreement, not just
until the end of
2010.
What will happen to rates during 2011-2015? The PUC doesn't
know. Before the Settlement, the amount of stranded cost recovery after
2010 was unknown (Order at 23), depending, for example, in part on the
payments required under GPU's contracts with NUGs that cannot be known
at this point with certainty. Those obligations remain, but the
Settlement fixes the amount of CTC collection after 2010 at the same
rate as collected from 2006-2010. It follows that,
unless none of the deferred stranded costs is actually collected
between 2011 and 2015, beyond what would have been collected without
the Settlement, customers will pay more for power. And to the extent
they do pay more, it is customers who will have actually funded the
POLR
payments, the shifting and deferring of accounts notwithstanding. We
think it is likely that customers will pay more, and that would explain
why GPU would agree to go to the trouble of establishing a deferred
account for stranded costs in the first place, instead of writing them
off when they are replaced in the CTC by POLR costs.
As to the terms in general, if the merger is consummated the PUC is
trying to have it both ways. Simultaneously with claiming customers
will pay nothing extra to GPU, the PUC asserts that the agreement
"adequately addresses GPU's current financial concerns" (Order at 10),
implying that Wall Street and GPU's creditors will be satisfied. But
will they? GPU estimates it will have bills for generation totaling
about $250 million this year that it can't pay out of current customer
generation revenue and still earn a fair return. The Settlement
provides no extra revenue through 2010. Yet GPU's financial problems
are supposed to disappear.
How? According to the PUC, it is because a regulatory asset (the
account for deferred POLR costs) has been created that it believes will
satisfy Wall Street and GPU's creditors. But, the problem is, as we
have explained, there are two regulatory assets being created-for
stranded costs as well as POLR costs-both of which can only be
collected through CTC rates that are fixed and remain unchanged by the
Settlement. As result, the Settlement has created regulatory assets
that, taken together through 2010, cannot produce even one dollar from
customers to pay GPU extra POLR costs.
The Settlement will help GPU pay its POLR creditors, though not because
any "asset" was created. Instead, the Settlement allows GPU to renege
on it NUG contracts and use the money to pay POLR bills. While this may
appear to "solve" a dilemma, at least in the short run, it not only
illegally changes the terms of GPU's Restructuring Settlement without
the consent of, and in some cases notice to, the signatories to that
agreement, it violates the terms of the contracts NUGs have with GPU
under federally mandated PURPA standards as well.
While this manipulation of accounts, debts, and contracts may
satisfy GPU's current creditors, it seems unlikely to convince Wall
Street that a lasting solution to GPU's POLR problems has been found.
The violation of the NUG contracts has already led to a swift appeal in
court of the
Order by ARRIPA, on behalf of the affected NUGs.
The PUC also doesn't seem to understand the terms of POLR collection
through the CTC as spelled out by the Settlement it has adopted. The
Order says GPU would collect POLR costs through the CTC "during the
years from 2006 through 2010" (Order at 20). This is incorrect. The
Settlement (paragraph 4) provides that, if the merger is consummated,
the CTC will be used to collect POLR costs "through 2010". Paragraph 2
of the Settlement allows GPU, "immediately upon entry of an order by
the PAPUC accepting this Stipulation," to defer its POLR costs incurred
from the first of this year for collection through the CTC. No mention
is made of waiting until 2006 to start collecting POLR costs, nor, of
course would it make any sense to do so. If GPU could not collect any
POLR costs until 2006 that would mean stranded costs would continue
through the CTC for the next five years with all of the POLR costs left
to be stuffed into CTC collections for the five years after that.
If the merger is abandoned for any reason, GPU ratepayers will pay a lot
of money.
If the merger is not consummated, things get drastically worse
for customers. The Settlement provides that GPU write off its POLR
costs incurred from the first of this year through May 30. But it then
guarantees that GPU will collect all of its remaining POLR costs
beginning June 1 until approximately the end of the year. Because power
is much more expensive in the summer, these costs are likely to total
more $150 million by GPU's estimates.
Stranded costs will be collected through the CTC as originally
intended; all deferrals of them will be eliminated. POLR costs will be
collected separately from, and in addition to, stranded costs, which
means only one thing: customer rates must rise. The "method and timing"
of such
rate hikes is left to the hearing that will commence 10 days after
merger abandonment. But the POLR costs will be collected. That is what
the order means when it says: "No such subsequent PAPUC determination
shall prevent the recovery of any deferred POLR costs accrued between
6/1/01 and the date of such final PAPUC order..."
By contrast, as previously explained, no such guaranteed
recovery exists if the merger is consummated. In that event, GPU will
collect as much of its POLR costs as it can through the CTC at a rate
fixed by the settlement. Any amount uncollected by 2010 must be written
off.
In order to recover stranded costs after this year, the Settlement
merely says GPU must show that such costs are "subject to normal
prudency [sic] and just and reasonable rate requirements applicable to
all utility expenditures." By its Order, however, the Commission has
already determined that GPU's sell-off of its generation and subsequent
wholesale purchases--which underlies its current and future claims for
cost recovery--were prudent. This should make it
relatively easy for GPU to continue to collect POLR costs beginning in
2002. Meeting the prudence standard will be simple in deregulated
markets: GPU need only show it paid the prevailing market price for
power.
Moreover, GPU's commitment to limit accruals of POLR costs only
through 2005 is contingent on the merger being consummated (paragraph 2
of the Settlement); it disappears if the merger is abandoned. In that
case, Met Ed and Penelec will be able to collect excess POLR costs
until the end of their transition periods, whenever that turns out to
be.
In summary, if the merger is abandoned the cost to ratepayers is likely to
be severe.
Is the merger likely to be abandoned?
Merger abandonment is no mere theoretical concern. It could happen for
one of several reasons: (1) the New Jersey BPU may reject the merger,
(2) The appeals court may overturn the PUC's approval of it, or (3)
FirstEnergy may itself abandon the merger for several reasons (GPU rate
relief being inadequate, delays preventing timely consummation, etc.).
Citizen Power is cautiously optimistic that the New Jersey BPU, which
has held hearings that have been much more thorough than those in
Pennsylvania, will reject the merger for the reasons similar to those
advanced by Citizen Power, i.e., that the Companies did not even come
close, and some cases didn't even try, to meet their statutory burdens
to show the merger would be in the public interest.
By tying POLR collection to the date of a PUC order to be issued in the
reopened POLR proceeding, the Settlement provides an incentive for the
Companies to delay announcing merger abandonment as long as feasible,
so that the PUC cannot issue an order before the end of the year. That
way, GPU will be able to collect all excess POLR costs incurred in
2001.
Consider this question. If you were GPU management faced with
this Settlement, you would have the following choice: (1) be acquired
by FirstEnergy, or (2) have guaranteed recovery of most of this year's
POLR costs, plus a strong basis, courtesy of the PUC's findings, for
recovering all POLR costs thereafter until the end of the transition
periods for Met Ed and Penelec. What would you do? We think GPU has
good reasons to choose the latter. It also appears that FirstEnergy may
have cooled a bit toward the merger because of GPU's cost problems and
the plummeting of GPU's stock price from its value when the merger deal
was announced.
On balance then, because it provides for guaranteed POLR cost
relief if the merger is abandoned, the Settlement seems to have
increased the chances that the merger will not be consummated, an
ironic result for those who have supported both it and the merger.
Maybe getting rate
relief and then abandoning the merger is just what FirstEnergy and GPU
management had in mind when they agreed to the Settlement.
Citizen Power, Inc.
July 19, 2001